AMRUT project delay deepens Aurad water crisis
BIDAR: The delay in completing the AMRUT 2.0 drinking water project has worsened the water crisis in Aurad constituency, where residents are already struggling with shortages due to deficient rainfall and drying up of local water sources.
The ₹84.82-crore project, intended to provide a permanent water supply to Aurad and Kamalnagar towns and nearby villages, remains incomplete despite receiving administrative approval nearly three years ago.
The project was approved in 2023, and the tender process was completed in January 2024. It was designed to draw water from the Karanja Reservoir and ensure a sustainable supply to the region under the Central Government-sponsored AMRUT scheme. The authorities had fixed January 2026 as the deadline for completing the work and commencing water supply. However, the deadline has passed without the project becoming operational.
Activists threaten agitation
Social activists have criticised the delay, alleging that officials have repeatedly cited various reasons instead of completing the work. They warned that people should not be made to suffer because of administrative delays and threatened to launch an agitation if the project was not completed immediately.
Members of the Nagarika Sangharsha Samiti also expressed dissatisfaction during a recent meeting with officials. They pointed out that District Minister Eshwar Khandre had earlier visited Tegampur Lake and instructed officials to take immediate measures to resolve the drinking water problem. However, they alleged that the expected action had not followed.
Clearances awaited
Officials of the Karnataka Urban Water Supply and Drainage Board (KUWSDB) said the project was facing delays in obtaining mandatory clearances. Forest Department permission is required for constructing water storage tanks, while National Highways Authority of India approval is necessary for laying pipelines along the highway.
Aurad MLA Prabhu Chavan blamed government negligence and the alleged non-release of funds to contractors for the delay. He urged residents to protest against the government.
KUWSDB Assistant Executive Engineer Shivakumar said the department had sought an additional one-year extension to complete the project. He added that work would be completed after receiving the necessary permissions.
With the crisis intensifying, residents have urged the government to intervene and ensure the project is completed without further delay.